On Singapore’s Global Switch Woodlands Data Centre, over 60 per cent of the mechanical, electrical and plumbing service modules were constructed and pre-commissioned while the structure was coming out of the ground. Working with Gammon, Aurecon’s modular approach of Design for Manufacture and Assembly (DfMA) reduced the programme by 30 per cent (from 18 to 15 months).

Together we reduced onsite plant and labour by 20 per cent. With much of the assembly undertaken at ground level before moving to site, we reduced the number of trades on site and cut down the amount of activity at heights to improve safety and reduce risk.

Our modular approach also reduced the potential for quality issues. Components were pre-integrated and pre-tested in a controlled factory environment using more comprehensive testing equipment, which enabled more rigorous testing and commissioning than is possible on-site.