Fanling Golf Course Environmental Enhancement, Hong Kong
Aurecon's ecologists conduct surveys and species monitoring at Fanling Golf Course to help preserve critical wildlife habitats in Hong Kong's lowland areas.
Change your location to view content tailored for you.
Aurecon contributes its structural and geotechnical engineering skills to Sha Tin Water Treatment Works, the largest water treatment works in Hong Kong, supplying approximately 30 per cent of the Territory’s total water demand.
Aurecon was appointed to take part in the Advance Works Contract for the expansion and in-situ reprovisioning of the aged South Works water treatment facility. The Advance Works Contract increases the facility’s treatment capacity from 364,000 cubic metres per day to 550,000 cubic metres per day, to meet fresh water demands from planned new urban housing developments.
Aurecon is designing the works that must be undertaken before demolition of existing facilities so that the main reprovisioning works can commence.
The major elements of works include:
The sloped terrain was a complex challenge due to the following reasons:

All works had to take place within the live operating environment of the water treatment plant. Aurecon developed an environment monitoring plan and confirmed each monitoring checkpoint location with resident site staff before carrying out the site works.
Safety was a primary focus throughout the design and construction stages.
Innovative design of the temporary works enabled Aurecon to eliminate the use of massive soil nail heads on temporary soil nails for slope stabilisation. By designing reinforcement to be placed near smaller nail heads, it avoided the need for temporary working platforms for soil nail head installation. This was a positive step in reducing the risk of workers falling from height.
Recognising the inherent safety demands of the site, Aurecon designed its steel structures with bolt connections, rather than welding connections to avoid hot works and to prioritise safety at all times.
Although construction is still ongoing, the project is already being recognised for its safety, environmental, and social considerations. In recognition of the design team that contributed to eliminating, reducing and mitigating the health and safety risks during the project, it was presented with the following awards: