Change your location to view content tailored for you.

Developed in the 1980s, Tseung Kwan O (TKO) is the seventh new town in Hong Kong that is home to a population of 414,000. To improve the district’s accessibility and to cope with the continuing increase in transport demand between TKO and East Kowloon, the Hong Kong Government worked on the Tseung Kwan O – Lam Tin Tunnel (TKO-LTT) as an additional and alternative highway route incorporating tunnel and bridges works.

Delivering engineering services

Aurecon was commissioned by Chun Wo – Shanghai Tunnel – China Metallurgical Joint Venture (CW-STEC-CMGC-JV) to deliver structural, geotechnical and temporary design works for the bridge component of the TKO Interchange and Associated Works project.

The project comprised the construction of an elevated interchange over the sea with seven post-tensioned concrete bridges. The interchange was erected with the use of the precast segmental balanced cantilever method. When completed, these bridges will also form a part of Route 6 – a major new link between the New Territories and Kowloon.

Location

Hong Kong

Client

Governement of Hong Kong – Civil Engineering and Development Department

Aurecon's Role

Bridge design, geotechnical works, temporary works design

Complete

2019

square iconplus icon
Aurecon was commissioned to deliver bridge design, geotechnical works and temporary work designs for Lam Tin Tunnel – Tseung Kwan O Interchange.
Tseung Kwan O is the seventh new town in Hong Kong and the bridges will improve the district's accessibility and cater to increased transport demand.
Forming a new strategic route network for the citizens of Hong Kong through TKO Lam Tin Tunnel and TKO Interchange.
The project comprises the construction of an elevated interchange over the sea with seven post-tensioned concrete bridges.
The drill and blast excavation for the new TKO Lam Tin Tunnel navigating through Hong Kong, the fourth most densely populated country in the world.
1 of 5
Aurecon was commissioned to deliver bridge design, geotechnical works and temporary work designs for Lam Tin Tunnel – Tseung Kwan O Interchange.
Aurecon was commissioned to deliver bridge design, geotechnical works and temporary work designs for Lam Tin Tunnel – Tseung Kwan O Interchange.
Aurecon was commissioned to deliver bridge design, geotechnical works and temporary work designs for Lam Tin Tunnel – Tseung Kwan O Interchange.

Winning over design challenges

Designing the interchange was not an easy feat. Challenges included designing and constructing the seven bridges over the marine zone that pose aggressive environmental conditions. Some of the project complexities included:

  • Heavy wave actions, onshore wind and water seepage
  • Highly curved road geometry alignments
  • Precast segmental single box deck
  • Balanced cantilever construction method
  • Narrow deck with complex structural details

Accurate assessments of exposure severity were vital to determine appropriate approaches with sufficient durability. According to the requirement, the bridges were designed and built for a design life of 120 years. To ensure the structure remains resilient to the extreme natural events, the piles for the bridges were founded in competent rock with some pile lengths exceeding 50 m.

With the bridges constructed over the sea, the geological longitudinal section of the rock goes as deep as 50 m below sea level requiring longer piles, while the bridge piers have piles cantilevering reaching to 20 m from the seabed. The team at Aurecon considered the method of erection, ensuring the geometry of the bridge superstructures met the required tolerances.

Geometry control work included the development of segment casting geometry, provision of segment data for individual segment match casting work at the precast yard and on-site erection geometry control work during segment erection. Aurecon also worked closely with the contractor to avoid step joints between the T-spans.

The bridges have extreme tight curvature with radii as low as 44 m, the geometric behaviour of the bridges is more complicated than straight bridges with inherent challenges. To address this, the project team avoided using external post-tensioning but adopted internal tendons. This approach saved the cost of erecting closely spaced deviators and resulted in better constructability.

Safety as the primary concern throughout the project

To successfully construct the precast segmental bridges in the marine zone with minimal disturbance to the natural environment, while providing design solutions for the works to be carried out safely, was also a challenge.

Aurecon strived to integrate safety in both the design and construction phases to ensure that workers were protected against any unnecessary exposure of potentially unsafe matters. This initiative also helps to reduce the amount of future maintenance works by enhancing the durability of the permanent works. Measures taken included:

  • Adopting precast shells to enhance work safety and reduce disturbance to the environment
  • Fulfilling the crack width limits on the pile cap shell to enhance durability; this helps reduce long term repair work and maintenance requirement at sea
  • Utilising modularisation to minimise manual works in the sea
  • Adopting a simpler method of shell installation and integration with permanent works
  • Deploying Aurecon’s in-house digital experts and developed 3D geometrical models for plate element analysis for clash detection and better determinations of design actions

This project is one of two contracts that Aurecon was enjoyed for as part of Tseung Kwan O – Lam Tin Tunnel (TKO-LTT). The other is the tunnel and associated works that connects to the interchange. Together, these two projects are a vital part of forming a new strategic route network for the citizens of Hong Kong.

Award-winning

The project won the following awards:

  • Winner: Hong Kong Institution of Engineers (HKIE) Structural Excellence Awards 2024 – Infrastructures and Footbridges (with Chun Wo)
  • Commendation: The Lighthouse Club International Design for Safety Awards 2019

We would love to work with you to bring your ideas to life, so get in touch and we'll get back to you.

Or contact an office near you.